How long does it typically take to have a water service connection/meter installed or Sewer Service Connection Permit issued?
Below are typical estimates only. Actual times are dependent on current workload.
• New, full water service connections (“dig-in”, main-to-meter): Approximately 3-4 weeks depending on current Lakehaven workload (allow additional 2 weeks if work in public ROW is required), after submitting payment.
• “Drop-in” water meter into existing meter setter: 2 weeks or less.
• Sewer Service Connection Permit (SSCP): 2-3 days (Residential), 3-5 days (Non-Residential); if work in public ROW is required, allow additional 2-3 weeks after submitting payment & prior to Lakehaven issuing a SSCP.

Show All Answers

1. What areas does Lakehaven provide water and sewer service to?
2. Where is the nearest existing water &/or sewer main line pipe in relation to my property?
3. Where can I obtain information about sewer service in the City of Edgewood?
4. What’s required to obtain a new or modified water and/or sewer service connection, or repair of an existing sewer service?
5. How can I obtain a copy of Lakehaven’s current design standards, construction/material specifications, and/or standard plan drawings?
6. How long does it typically take to have a water service connection/meter installed or Sewer Service Connection Permit issued?
7. Do I need a “Certificate of Availability”?
8. If my property is within Lakehaven’s water and/or sewer service area(s), am I required to connect my property/building(s) to Lakehaven’s water and/or sanitary sewer system?
9. Will obtaining a service connection require me to construct additional system facilities (mainline, hydrants, manholes, etc.)?
10. What do I do if a Developer Extension Agreement is required?
11. Who installs service connections?
12. How do I locate utility services before I accidentally dig them up?
13. Who should I contact with other or additional questions?